How to build a preventive maintenance plan, with a template
A preventive maintenance plan is a list of what gets checked on each machine, how often and by whom. You can put one together in an afternoon in five steps; the hard part isn't writing it, it's sticking to it.
Updated on
What a preventive maintenance plan is
A preventive maintenance plan is a document — in practice, a table — that says, for each machine, which maintenance tasks need doing, how often, who does them and where it’s recorded that they were done.
It isn’t a technical manual or an engineering study. For a workshop, a plant or a commercial kitchen, a good maintenance plan fits on one sheet and can be put together in an afternoon. What makes it good isn’t its length, it’s that it reflects what can actually be done.
It has three goals: fewer breakdowns, no breakdowns caused by something you could have seen coming, and maintenance spending you can predict.
Step 1: build the machine inventory
You can’t plan maintenance for machines nobody has listed. The first step is a list with, at least:
- A name and a unique ID (an asset code, the serial number).
- Make and model.
- Location: building, area, line.
- Purchase date and supplier.
- Where its manual is.
Use the opportunity to rate each machine by criticality: what happens if it stops tomorrow? If the answer is «the workshop stops», it’s critical. If it’s «we use another one», it’s important. If it’s «we replace it this afternoon», it’s secondary. That rating decides how much effort it gets.
Step 2: decide the tasks for each machine
For each machine, list its preventive maintenance tasks. The sources, in order:
- The manufacturer’s manual: it almost always includes a maintenance table with tasks and intervals. Copy that first.
- Regulations, if the machine is covered: lifting equipment, pressure vessels, gas, fire protection. Those inspections aren’t optional.
- The breakdown history: if a part fails often, its check goes into the plan even if the manual doesn’t ask for it.
- The technician’s experience: they know what gets dirty, what works loose and what makes a noise before it breaks.
Typical tasks are few and they repeat: clean, lubricate, check settings and fastenings, replace filters and consumables, check levels, calibrate and inspect visually.
Step 3: set the frequency
Every task needs a frequency. Choose between:
- By calendar: daily, weekly, monthly, quarterly, yearly. Easiest to stick to.
- By usage: running hours, cycles, miles. More precise, but it only works if someone keeps count.
Start with the manual’s interval. Then adjust with data: if three inspections in a row find nothing, it can probably be spaced out; if the machine fails between inspections, bring them closer.
Write the interval down as a number, not as a feeling. «Every 3 months» can go in a calendar; «from time to time» can’t.
Group tasks with the same frequency into a single inspection. «Quarterly compressor service» with five points inside gets done far more reliably than five separate tasks.
Step 4: assign owners and records
A task without an owner doesn’t get done. For each inspection, decide:
- Who does it: a specific technician, the machine operator or an outside contractor.
- Where it’s recorded as done, with the date, who did it and what was found.
The record is the most neglected part and the most valuable. Without it you can’t prove a mandatory inspection, tell whether the plan works or adjust the intervals.
Step 5: schedule it and review it
With the frequencies decided, spread the inspections across a preventive maintenance schedule. Avoid having them all land in the same week and use the downtime you already have: shift changes, holiday shutdowns, quiet days.
Every few months, review the whole plan: new machines or retired ones, inspections that never happen, breakdowns the plan didn’t prevent. A plan nobody reviews is out of date within a year.
Preventive maintenance plan template
This template is a starting point. Copy it into a spreadsheet and add one row per task:
| Machine | ID | Criticality | Task | Frequency | Owner | Last done | Next due | Notes |
|---|---|---|---|---|---|---|---|---|
| Screw compressor | CMP-01 | Critical | Replace air filter, check oil level | Quarterly | In-house technician | 15 Jul | 15 Oct | |
| Screw compressor | CMP-01 | Critical | Full manufacturer service | Yearly | Outside service | 3 Feb | 3 Feb | Keep the report |
| CNC lathe | TRN-02 | Critical | Clear chips, lubricate ways, check coolant | Weekly | Operator | 18 Oct | 25 Oct | |
| Forklift | CAR-01 | Important | Check brakes, forks and battery | Monthly | In-house technician | 1 Oct | 1 Nov | Annual statutory inspection separate |
| Fire extinguishers | EXT-01…08 | Mandatory | Visual check | Quarterly | In-house technician | 30 Sep | 30 Dec | Annual service by an approved company |
The two columns that matter most are Last done and Next due: they tell you at a glance what has fallen behind.
The one-page weekly schedule
The template above is the plan. What gets stuck on the wall next to the machines is a simpler sheet: the week, with one box per check. Print one per month:
| Machine | Check | Mon | Tue | Wed | Thu | Fri | Initials |
|---|---|---|---|---|---|---|---|
| CNC lathe TRN-02 | Clear chips, check coolant | ☐ | ☐ | ☐ | ☐ | ☐ | |
| CNC lathe TRN-02 | Lubricate ways | ☐ | |||||
| Compressor CMP-01 | Drain condensate, check pressure | ☐ | ☐ | ☐ | |||
| Forklift CAR-01 | Brakes, horn, forks before first use | ☐ | ☐ | ☐ | ☐ | ☐ | |
| Band saw SRR-01 | Blade tension and guides | ☐ |
Keep it short: if the sheet has more than fifteen lines, nobody fills it in. The daily checks belong to the operator; the rest go in the plan with their owner. For the list of checks by frequency, see the preventive maintenance checklist for small workshops.
Common mistakes in a small workshop’s first plan
- Copying a big plant’s plan. Two hundred tasks on twenty machines get abandoned in a month. Start with the critical machines and five tasks each.
- Frequencies without a reason. “Monthly” because it sounds right. Use the manual and the breakdown log: if a check never finds anything in a year, space it out.
- No owner. A task assigned to “maintenance” is assigned to nobody.
- No record. If you can’t show when the forklift brakes were last checked, for an inspector or an insurer they weren’t.
Why a spreadsheet plan falls short
A spreadsheet template is the sensible way to start. Its limits show up within a few months:
- It doesn’t remind you. The next due date is written down, but nobody looks at it until it has passed.
- It lives on one computer. The inspection happens on the shop floor and gets recorded — if it does — hours later in the office.
- It doesn’t link inspections and breakdowns. The plan sits in one place and the breakdown history in another, so it’s hard to see whether a machine with up-to-date inspections keeps failing.
- It doesn’t total costs per machine without formulas that somebody eventually breaks.
Devian is an app for iPad, iPhone and Mac built for that next step. Every machine has its record and its inspections with an interval in months, with a reminder when one is due. Marking an inspection as done logs the preventive job in the history on its own, next to the breakdowns and what each one cost. If your template is already in a spreadsheet, the CSV importer brings the machines in at once, and everything can be exported again as CSV and PDF. It’s a tool for a workshop where everyone knows each other, not a maintenance management system for a large plant.
Frequently asked questions
What should a preventive maintenance plan include?
At minimum: the list of machines, the tasks for each one, how often each task is done, who does it and where it's recorded as done. That's enough to start; estimated costs and spare parts can come later.
How often should preventive maintenance be done?
The manufacturer's manual is the starting point. Then adjust with experience: if an inspection never finds anything, it can be spaced out; if the machine fails between inspections, bring them closer together.
Is a spreadsheet template good enough for a maintenance plan?
To get started, yes. Its limits show up with use: it doesn't remind anyone when an inspection is due, it lives on one computer, and it doesn't link the inspection to the machine's breakdown history.
What about inspections required by law?
Put them in the same plan, flagged, with their legal frequency, and keep the certificate or report for each one. That way the plan also proves they were done.