Types of maintenance: preventive, corrective and predictive
Three types of maintenance matter in a workshop: corrective, which fixes what has broken; preventive, which checks before it breaks; and predictive, which measures to know when it will break. None of them is enough on its own.
Updated on
The three types of maintenance, one sentence each
Search for «types of maintenance» and you’ll find lists of five, seven or ten categories. Almost all of them are variations on three ideas:
- Corrective maintenance: you repair what has already broken.
- Preventive maintenance: you inspect and replace before it breaks, following a calendar or hours of use.
- Predictive maintenance: you measure the machine’s condition and step in when the data says something is starting to go wrong.
There are more names — total productive maintenance, operator maintenance, improvement maintenance — but for a workshop, a plant or a commercial kitchen what matters is understanding these three, knowing what each one costs and deciding where to use which.
Corrective maintenance: fix it when it fails
This is the one everybody does, whether they mean to or not. The machine stops, someone looks at it, the part gets replaced and it runs again.
It comes in two flavours:
- Immediate corrective: the fault forces you to stop now. This is the expensive case, because on top of the repair you pay for the downtime: lost output, people waiting, orders running late.
- Planned (deferred) corrective: you detect a fault that still lets you work — a noise, a small leak, a sensor that fails now and then — and repair it when it disrupts least.
Corrective maintenance isn’t bad in itself. For a cheap machine that’s replaced in an hour and whose downtime holds nobody up, waiting for it to fail is the most economical choice. The trouble starts when it’s the only kind of maintenance: every breakdown becomes a surprise and the workshop lives in firefighting mode.
What gets lost most in corrective work isn’t the part, it’s the information. If nobody records what failed, when and what it cost, next time the diagnosis starts from scratch and you never learn which machine is causing the most trouble.
Preventive maintenance: check before it breaks
Preventive maintenance means stepping in before the breakdown, following a plan: change the oil every so many hours, check belts every three months, calibrate a scale every year, clean filters every week.
Inspections are scheduled in two ways:
- By calendar: monthly, quarterly, yearly. It’s the simplest option and works best when the machine’s use is fairly steady.
- By usage: every 500 hours, every 10,000 cycles, every so many miles. It’s more precise, but it means keeping count of hours or cycles.
What preventive maintenance gets you:
- Fewer unplanned stops, and shorter ones when they do happen.
- Machines that last longer, because wear is dealt with before it builds up.
- Predictable spending: you know what’s due this month and roughly what it will cost.
- For a lot of equipment — lifting gear, pressure vessels, gas, fire extinguishers — it’s also a legal requirement, with periodic inspections you must be able to prove.
What it costs:
- Technician time on inspections that sometimes find nothing.
- Parts replaced while they still have life left.
- Discipline: a preventive plan nobody follows is worse than none, because it gives a false sense of control.
The rule of thumb is to apply preventive maintenance where downtime costs more than the inspection. The press that stops the whole line, yes. The office fan, probably not.
Preventive maintenance checklist for a small workshop
Most guides stop at the definitions. This is the checklist a ten-to-thirty machine workshop can start using on Monday. Adapt the tasks to each manufacturer’s manual: the manual always wins.
Daily (operator, 5 minutes per machine)
- Walk around the machine: oil, coolant or air leaks.
- Listen for new noises and feel for new vibration at start-up.
- Guards, emergency stops and interlocks in place and working.
- Clear chips, dust and offcuts; clean the work area.
- Check gauges and warning lights against their normal readings.
Weekly
- Lubricate ways, chains and grease points as the manual specifies.
- Check coolant and hydraulic oil levels; top up and note how much.
- Drain compressed-air condensate.
- Clean or check intake and extraction filters.
Monthly
- Inspect belts and chains for tension and wear.
- Check forklift brakes, forks, tyres and battery.
- Test safety devices: light curtains, two-hand controls, limit switches.
- Tighten loose fasteners on machines that vibrate.
- Visual check of electrical cables, plugs and cabinets (no opening live panels).
Quarterly
- Change filters and fluids on critical machines (compressors, hydraulics).
- Check alignment and backlash on precision machines.
- Review the breakdown log: which machine failed most and why.
Yearly
- Manufacturer or outside service on critical machines; keep the report.
- Statutory inspections: lifting gear, pressure vessels, fire extinguishers, gas.
- Recalibrate measuring equipment.
- Review the whole plan: drop tasks that never find anything, add the ones the breakdown log asks for.
Two rules make the checklist work: write down the date and who did each task, and turn every repeated breakdown into a new line on the list. To turn this into a full plan with owners and due dates, see how to build a preventive maintenance plan.
Predictive maintenance: measure to know when
Predictive maintenance goes one step further: instead of inspecting by calendar, it measures the real condition of the machine and acts when that reading changes. It’s the difference between changing the oil every 500 hours no matter what and changing it when an analysis says it has degraded.
In large industry this is done with sensors and specialist techniques: vibration analysis, thermal imaging, oil analysis, ultrasound, power monitoring. It makes a lot of sense on critical, expensive equipment, and very little in a ten-machine workshop.
But the idea scales down without buying anything:
- Log hours of use and notice when a machine is reaching its limit sooner than expected.
- Note temperatures, pressures or consumption at each inspection and watch the trend.
- Look at the breakdown history: if a pump has failed three times in six months, the next failure isn’t a surprise, it’s a prediction.
That last point is the cheapest predictive maintenance there is, and it only needs one thing: a recorded history.
Preventive and corrective maintenance: how to combine them
In practice nobody picks a single type. The sensible move is to sort your machines and decide for each group:
| Type of machine | What fits | Example |
|---|---|---|
| Critical: its downtime stops the work | Strict preventive, plus predictive if something can be measured | Main compressor, press, oven |
| Important, with a fallback | Light preventive and planned corrective | Second line, spare forklift |
| Cheap or easy to replace | Corrective | Power tool, fan |
| Legally required inspections | Preventive as the regulations say, with records | Lifting gear, pressure, extinguishers |
To turn this table into more than a theory exercise you need three facts about each machine, and they’re usually missing:
- What its downtime costs, even as an estimate.
- How many times it has failed, and why.
- How much has been spent on it: labour, parts, outside technicians.
With those, deciding where to put preventive work stops being a hunch. If a machine piles up breakdowns and cost, it needs inspections. If it rarely fails, corrective is cheaper.
Where to record all of this
Most small businesses start with a spreadsheet: one tab for machines, one for breakdowns, one for inspections. It works until it doesn’t: the spreadsheet lives on the office computer, the breakdown happens on the shop floor, and what gets written down «later» rarely gets written down.
Devian was built for exactly that. It’s an app for iPad, iPhone and Mac that keeps the inventory with a record for every machine, the history of each breakdown with what it cost in labour and parts, and recurring inspections that remind you when they’re due. Completing an inspection logs its preventive job on its own, so preventive and corrective work end up in the same history. It isn’t a maintenance management system for a large plant: it’s meant for a workshop with five to a hundred machines that runs on a spreadsheet today, and it can import that spreadsheet as CSV.
Frequently asked questions
What is the difference between preventive and corrective maintenance?
Corrective maintenance happens after the breakdown: the machine fails and gets repaired. Preventive maintenance happens before, with inspections scheduled by calendar or by hours of use, so the breakdown never arrives. Corrective work is unavoidable; preventive work is there to make it the exception rather than the routine.
Is predictive maintenance only for large companies?
The version with sensors, vibration analysis and thermal imaging usually is. But the underlying idea — measure something and act when the reading changes — works on a small scale too: log hours of use, temperature or power draw and inspect when they drift from normal.
Which type of maintenance suits a small business?
A mix: preventive on the machines whose downtime is expensive, corrective on the ones that are cheap or quick to replace, and a breakdown log that tells you which are which. Without that log, the decision is guesswork.
What goes on a preventive maintenance checklist for a small workshop?
Short daily checks done by the operator (leaks, noises, guards, cleaning), weekly lubrication and filter checks, monthly checks of belts, brakes and safety devices, quarterly fluid and filter changes on critical machines, and the yearly manufacturer services and statutory inspections. The checklist in this guide lists them by frequency.
What is planned corrective maintenance?
It's a fault that doesn't force you to stop right away: you spot it, log it and fix it when it disrupts least, such as at a shift change or over a weekend. It's still corrective, just without the emergency.